Thunder Ridge - 9/28/22

Image
Striping at the new south entrance. Parking lot 4A getting striping done today. Survey crew marking the layout now. Entrance coming off of the north pedestrian trail. View of the north suites. View of the south suites. Stage and floor level seating getting set up. Concert starts tomorrow and runs through the weekend.

Thunder Ridge - 9/27/22

Image
Chip & seal going down on parking lot 4A. Turf has been installed in front of north suites. Prepping the south suites for turf install. Springfield Striping at the south entrance. Getting their measurements. View of the area where the ditch is supposed to be cut in. Other side should have ditch line as well. Supposedly an agreement has been made to wait until after the concert to fully complete this part of the job.

Thunder Ridge - 9/26/22

Image
Digging out area in front of suites to install turf. Building up parking lot 4A. Bringing in the base to get spread and compacted. Base getting rolled as it’s spread. Compaction testing done once the lot was compacted and had good results. Ready for chip and seal.

Thunder Ridge - 9/22/22

Image
Compaction testing for parking lot 8. Mulch has been laid along the edge of the pedestrian trails and the crews have it ready for the event. Several crews still working on getting the suites put together. Stuff coming in and pop up tents installed to show off products. Boats, Utv’s, etc.

Thunder Ridge - 9/21/22

Image
Getting ready to pour the remaining section of the south pedestrian trail. Concrete tested out good and the pour is underway. Pour is complete. All went well, just smoothing out the surface now. Power washing the concrete to get the exposed aggregate look the client wants. Rebar set for the footings at the entrance of parking lot 3. Concrete has arrived and the pour is underway. Smoothing out the surface. No issues.

Thunder Ridge - 9/20/22

Image
Concrete pour for the remaining part of the north pedestrian trail. Forms are set and ready to go. Concrete pour is underway. Concrete tested out good. Wrapping things up with the last truck of the day. Surface smoothed out. Hydroseeding the edge of roadway on Hwy 86.

Night 14 - Hwy 86 Improvements

Image
 First truck arrived at 8:30pm to complete the base on the south side of Hey 86 on Modot RoW. Crews then continued to lay base up the hill to connecting driveway before switching to surface mix, capping the driveway portion. Starting on the West End Before First Lift Second Lift