Thunder Ridge - 9/21/22
Getting ready to pour the remaining section of the south pedestrian trail.
Concrete tested out good and the pour is underway.
Pour is complete. All went well, just smoothing out the surface now.
Power washing the concrete to get the exposed aggregate look the client wants.
Rebar set for the footings at the entrance of parking lot 3.
Concrete has arrived and the pour is underway.
Smoothing out the surface. No issues.