Night 5 - Hwy 86 Improvements
Crews arrived at 7 PM to set up traffic control and continue grading operations after removing edge treatment throughout the project. Concrete Cutting and Coring completed sawing cutting edge of pavement on the North side of Hwy 86. ESS began installing base rock and edge treatment on the East end of the project to the entrance of Lot 8 around 1 AM.