Thunder Ridge - 9/27/22
Chip & seal going down on parking lot 4A.
Turf has been installed in front of north suites.
Prepping the south suites for turf install.
Springfield Striping at the south entrance.
Getting their measurements.
View of the area where the ditch is supposed to be cut in.
Other side should have ditch line as well. Supposedly an agreement has been made to wait until after the concert to fully complete this part of the job.