Thunder Ridge - 8/31/22

Image
Chip and seal on lot 4. Once finished here they will move to lot 3. It’s been compaction tested and is ready for them. Getting rebar installed for the north suites footing. View of the south suites retaining wall. Work being done on the south suites. View of the rock stairway that leads up to the main building. Lot 8 is being compacted. Chip and seal crew has moved over and started working on lot 3 now that 4 is finished up. Rebar for the south footing. Pour tomorrow morning. Changes to the layout causes us to move columns over so have to pour again for these. South side.

Night 2 - Hwy 86 Improvements

Image
 Traffic control in place at 8 p.m. ESS began stripping top soil and grading operations along the North side of Hwy 86. Proof rolling was completed at 3:30 a.m. One small area was found to be removed and replaced with adequate fill material. Edge treatment was maintained or installed throughout the project. Cleaning operations were completed and traffic control was removed by 6 a.m. Before Grading Operations. East of Lot 8 Entrance After Grading Operations. West and East of Lot 8 Entrance Weather 8 - 30- 2022

Thunder Ridge - 8/30/22

Image
Finishing the forms for the south retaining wall pour today. Getting rebar ready for the north keyway pour today. Pour for the wall has begun. Concrete tested out good. Rebar on the north side ready for concrete. Pour for the north keyway has begun. Concrete tested good. Pour complete. No issues.

Night 1 - Hwy 86 Improvements

  Rain began at approximately 7 p.m. Traffic control Contractor laid out signs on both ends of the project at 8 p.m. in the rain. Light fog moved in with continued rain at 9 p.m. To avoid excessive mud on Hwy 86 throughout the week and extensive clean up hours, the decision was made to not strip top soil. 

Thunder Ridge - 8/29/22

Image
Lot 2 excavation of soft soil. Will be backfilled and compacted afterwards. North suites area. Waiting on south suites to get wrapped up. Decorative rock being placed all along the stairway leading up to the main building. Setting forms for the retaining wall on the south suites. View from the top of the stairway. Chip and seal being installed on lot 4. Crew is delayed due to the weather. Will finish this lot then move to lot 3. Excavating soft spots in lot 2. Chip and seal done for the day. North suites footing. South suites retaining wall. Lot 2 ready for base and compaction.

Thunder Ridge - 8/26/22

Image
Concrete pour this morning for the stairs on the north side. North suites footing area. South suites footing area. Retaining wall rebar install. Concrete pour completed. North suites footing area. Stripping forms from the stairway. Rock going on top of the previously poured stairway. Retaining wall rebar install on the south suites.

Thunder Ridge - 8/25/22

Image
Crew getting the rebar installed for the south suites footing. View from the top. Columns going in front of the footing. Stairway crew getting rock set on top. Finishing up rebar for the columns before the pour. Pour has begun. Concrete tested good. Finished product. KEI crew working on getting the north stairs forms set again. Have to match the south side. Error the first time. North suites footing area.