Finishing the forms for the south retaining wall pour today.


Getting rebar ready for the north keyway pour today.




Pour for the wall has begun. Concrete tested out good.


Rebar on the north side ready for concrete.


Pour for the north keyway has begun. Concrete tested good.




Pour complete. No issues.