Thunder Ridge - 8/22/22



Keyway dug out. Rebar set for concrete pour tomorrow.








A concrete pour for the stairway leading up to the main building took place today. Had some issues with low air but was able to get it resolved by adding airpods to get it up to 5%-7%. Yards delivered = 76. Cylinders taken = 10.




Stairway on the northwest side was not poured due to errors in how it was laid out. Not symmetrical with the southeast side. Will get fixed and poured at a later date.