Night 10 - Hwy 86 Improvements

Crews arrived at 6 PM to set up traffic control shortly after. ESS removing edge treatment throughout the project in preparation for paving operation that night. First truck onsite at 8:30 PM.  Base rock was removed from parking lot entrance 8. Grade was made, and compaction completed in this area before the paver reached this point. Completed 1st lift and part of 2nd lift on night 1. Paving operations off the road just before 6 AM.



Weather


Start of Paving Operation at Sta 180+00