Night 11 - Hwy 86 Improvements

Crews arrived at 6 PM to set up traffic control shortly after. ESS broomed the new surface in preparation for paving operations that night. New surface was tacked before first truck onsite at 7:45 PM.  Paving completed on the Hwy 86 Phase 1, North side widening night 2. Paving operations off the road by 11:30 PM. Paving crew moving down to parking lot entrances at the Arena. Dirt Crew began asphalt edge removal at the Future Entrance at STA 155+00. Crews off the road before 6AM.



Weather


Night 2 Paving Operations


Handwork at Taper