Night 6 - Hwy 86 Improvements
Crews arrived at 7 PM to set up traffic control shortly after. ESS continue grading operations after removing edge treatment throughout the West end of the project. Removal of the replacement of the entrance to Parking lot 8 was completed. ESS began installing base rock and edge treatment on the West end of the project to the entrance of Lot 8 for the remainder of the night.
Weather
Removal of dirt Entrance to Lot 8
Removal of dirt Entrance to Lot 8
Grading Completed on the West end of the Project
Installation of Base Rock Edge Treatment