Night 8 - Hwy 86 Improvements

Crews arrived at 7 PM to set up traffic control shortly after. ESS continued installing and grading base rock after removing edge treatment on the West end of the project. Base rock was placed and compacted on the West end to Parking Lot 8 Entrance. ESS began installing base rock as edge treatment on the West end of the project for remainder of the night. All base rock was watered to harden over the weekend.



Weather


Base Rock Grading


Base Rock Prior to Compaction