Thunder Ridge - 9/3/22



Column pads are ready to go on the north suites. Crew is working on getting the footing part ready. Pour got pushed back from 7:00 to 8:00. Rain yesterday caused delays.






Pour is underway. Concrete tested out good. Starting with the column pads.




Moved over to the footing section.


View of the south suites. Getting ready to pour the retaining wall extension that was put in.


Pour is complete.


View of the new walkway between the stairs and the main building. Rock being placed on top of the concrete.