Thunder Ridge - 9/8/22
Getting ready to pour the deck of the south suites.
Edge of wall showing the drainage pipe and gravel backfill.
Concrete pour is underway. Tested out good.
Concrete pour complete. No issues.
South suites ground level. Getting prepped for concrete.
South pedestrian trail being formed up.
North suites retaining wall extension getting formed up. Plan to pour this tomorrow morning.
Have to reset where the guardrail will be going in parking lots 2 and 3 due to erosion issues.