Traffic control in place at 8 p.m. ESS continued grading operations along the North side of Hwy 86 after removing edge treatment. Concrete Cutting and Coring onsite to continue cutting edge of existing roadway west of lot 8 entrance. Thunderstorms started at 11:30 p.m. Crews worked to install silt sox and edge treatment in areas where finish grade was made on the East end and throughout the project. Cleaning operations were completed and traffic control was removed by midnight. Weather Finish Grading
Traffic control in place at 8 p.m. ESS began stripping top soil and grading operations along the North side of Hwy 86. Proof rolling was completed at 3:30 a.m. One small area was found to be removed and replaced with adequate fill material. Edge treatment was maintained or installed throughout the project. Cleaning operations were completed and traffic control was removed by 6 a.m. Before Grading Operations. East of Lot 8 Entrance After Grading Operations. West and East of Lot 8 Entrance Weather 8 - 30- 2022
Crews arrived at 7 PM to set up traffic control and continue grading operations after removing edge treatment throughout the project. Concrete Cutting and Coring completed sawing cutting edge of pavement on the North side of Hwy 86. ESS began installing base rock and edge treatment on the East end of the project to the entrance of Lot 8 around 1 AM. Weather Grading Base Rock Edge Treatment
Comments
Post a Comment