Traffic control in place at 8 p.m. ESS continued grading operations along the North side of Hwy 86 after removing edge treatment. Concrete Cutting and Coring onsite to continue cutting edge of existing roadway west of lot 8 entrance. Thunderstorms started at 11:30 p.m. Crews worked to install silt sox and edge treatment in areas where finish grade was made on the East end and throughout the project. Cleaning operations were completed and traffic control was removed by midnight. Weather Finish Grading
Traffic control in place at 8 p.m. ESS began stripping top soil and grading operations along the North side of Hwy 86. Proof rolling was completed at 3:30 a.m. One small area was found to be removed and replaced with adequate fill material. Edge treatment was maintained or installed throughout the project. Cleaning operations were completed and traffic control was removed by 6 a.m. Before Grading Operations. East of Lot 8 Entrance After Grading Operations. West and East of Lot 8 Entrance Weather 8 - 30- 2022
Chip & seal going down on parking lot 4A. Turf has been installed in front of north suites. Prepping the south suites for turf install. Springfield Striping at the south entrance. Getting their measurements. View of the area where the ditch is supposed to be cut in. Other side should have ditch line as well. Supposedly an agreement has been made to wait until after the concert to fully complete this part of the job.
Comments
Post a Comment